Caland Mine Headframe Atikokan, ON for MNDM Denison Environmental Services Setting the standard In the fall of 2000, the Ontario Ministry of Northern Development and Mines awarded the 3rd phase of the cleanup work at Caland to DES. This involved the demolition of the Headframe and Administration structures. The Caland Mine Headframe, Auxiliary Building demolition and subsequent shaft capping was complete on March 30, 2001. For more information on how we may help with your closure activities email Ian Ludgate at info@denisonenvironmental.com.
|
|
|